​Assignment

In April 2013 Polish P&DS team signed an exclusive framework agreement for Construction Management and Project Management Service with Tristan/Alianz, the owners of the landmark office building  - the Warsaw Financial Centre - in respect of the planned refurbishment works and future office fit-out projects. WFC offers c.a. 51,000 sq. mof leasing area. 

Actions

  • Defining the Client’s requirements, designers supervision, cost estimation, value engineering
  • Negotiations of the construction costs, preparation of adequate Lease agreement appendices on behalf of both parties.
  • Construction Management of all works connected with fit-out of the new office space, cost control, and payments monitoring,  progress monitoring, detailed and regular reporting 
  • Supporting the on technical matters after completion of the project

Results

  • The existing contactors review was conducted leading to savings 

  • Efficient reporting and decision making process optimized input of the Client, allowing to focus both WFC and Tenant on their core business and to having full control of the project in the same time  

All Case Studies

 

 

Valuation of ProLogis portfolio in Poland/poland/en-gb/case-studies/10/valuation-of-prologis-portfolio-in-polandValuation of ProLogis portfolio in Poland
Project management for ABN AMRO, Warsaw/poland/en-gb/case-studies/11/project-management-for-abn-amro-warsawProject management for ABN AMRO, Warsaw
Factory Outlet - First outlet centre in Poland, Warsaw/poland/en-gb/case-studies/12/factory-outlet-first-outlet-centre-in-poland-warsawFactory Outlet - First outlet centre in Poland, Warsaw